Related articles:
The Adjust Progress Report Schedule feature gives you the capability to change the next Progress Report due date.
This feature should be used when the referral date is not accurate due to claim transfers from another firm or when you have dual claims and want to sync the PR due dates to meet L&I requirements.
To adjust the PR due date, go on the Reports tab when a due Progress Report is present and click on the link:
Enter the new PR due date and Apply New Date:
Note: If you don't see the option to adjust the PR schedule, check to confirm that the case is an L&I case and/or that there is a pending PR that can be scheduled.
Once a PR due date is rescheduled, remember to use the Reset button when you start writing the PR in order for information to auto-populate (for more details, please see the related article at the top of the page).
The following PR due date is scheduled 30 days after the current PR is submitted, regardless of whether it was submitted early or late.